All encompassing Demolition and Land Remediation package on this redundant 62 acre steam locomotive/generator works site.
Project Highlights:
2500 tonnes of asbestos removal
Demolition of over 20 acres of industrial buildings
Earthworks operations of 350,000m3 cut and fill to create desired development levels
Removal and recovery of over 30 acres of reinforced concrete slabs and foundations to create recycled aggregates and fills for re-inclusion within the works – graded to Type 1, 6F1 and 6F2
Service disconnections, diversions, protection and reinstallation
Infrastructure and section 106 highway works
Lump Sum, All Risk package.