Trent Valley Four Tracking Project -
Back to last pageProject Value: £25m
Client: Network Rail
click a small image below to enlarge

450,000m³ of Earthworks to widen the West Coast Mainline Railway

Capping layer for railway construction - 40,000m³

10km of new drainage infrastructure

25 culvert extensions and associated RC works

Extensive Piling for 450 No OHLE and Signal Gantry Structures, including use of Network Rail Piling Train

RC bases for OHLE & Signal bases

35,000m of Cable Troughing

160,000 tonnes of Bulk Ballast works – with GPS Machine Control achieving excellent quality level control

RC Retaining Walls

Soiling, seeding and protection netting to 13km of embankments

Traffic Management and Signalisation works for Plant Crossings