Openshaw West Constraints Removal Works

Client: Manchester City Football Club
Value: £15.1m
Size: 83 acres (32,000m²)
Location:
Manchester
Completion:
2013

The demolition and remediation of a site to facilitate the construction of Manchester City Football Club’s Training Facility.  Facts and Figures:

  • Volume of Material Remediated: Circa 2 million tonnes
  • Volume of Material Remediated Contaminated with Coal Tar: 100,000m³
  • Material Imported / Exported: ZERO- 137,000m³ of recycled aggregate was taken from below ground obstructions and structures and reused as part of MCFA development
  • Recycled Material: £450,000 of recycled metals
Client: Manchester City Football Club
Size: 83 acres (32,000m²)
Location: Manchester
Completion: 2013
Value: £15.1m

The demolition and remediation of a site to facilitate the construction of Manchester City Football Club’s Training Facility.  Facts and Figures:

  • Volume of Material Remediated: Circa 2 million tonnes
  • Volume of Material Remediated Contaminated with Coal Tar: 100,000m³
  • Material Imported / Exported: ZERO- 137,000m³ of recycled aggregate was taken from below ground obstructions and structures and reused as part of MCFA development
  • Recycled Material: £450,000 of recycled metals