Salford Phase 1 Remediation

Client: Peel Land (Red City) Ltd
Value: £4.2m
Size: 45 acres
Location:
Manchester
Completion:
2010

Significant site remediation and preparation work for the construction of the City of Salford Community Stadium to bring 45 acres of derelict land back into use for the community, bringing considerable social and economic benefits to Salford.

Our third party approved remediation strategy was based on a sustainable approach of forensic segregation/processing/recycling to maximise reuse of site-won materials.

Innovative construction solutions:

  1. Delivered zero waste to landfill
  2. Imported aggregate created from:
    a. 85% of processed site-won materials
    b. 15% procured from a recycled sourced within 15 miles
Client: Peel Land (Red City) Ltd
Size: 45 acres
Location: Manchester
Completion: 2010
Value: £4.2m

Significant site remediation and preparation work for the construction of the City of Salford Community Stadium to bring 45 acres of derelict land back into use for the community, bringing considerable social and economic benefits to Salford.

Our third party approved remediation strategy was based on a sustainable approach of forensic segregation/processing/recycling to maximise reuse of site-won materials.

Innovative construction solutions:

  1. Delivered zero waste to landfill
  2. Imported aggregate created from:
    a. 85% of processed site-won materials
    b. 15% procured from a recycled sourced within 15 miles